CAPACITOR BANKS at the 121 kV 25 MVA SUBSTATION “UST-OMCHUG”

Customer OJSC „Magadanenergo”, Russia

By the end of March 2014, OJSC “Magadanenergo” has completed the reconstruction of the high-voltage line (HVL) "Ust-Omchug - Omchak." It is designed to smooth power supply to the mines "Pavlik" and "Matrosov Gold Mine." Also for power supply of gold mining companies the company "Magadanenergo" reconstructed 220 kV Ust-Omchug substation. There they installed a new transformer, a modern system of relay protection, automation, as well as capacitor banks, provided by LLC "Clever Reactor". Specialists have conducted a comprehensive testing of the devices, it has been successful.

Ust-Omchug substation and HVL "Ust-Omchug - Omchak" will meet the needs of the first startup complexes of gold processing plants at “Natalka” deposit and "Pavlik” gold mine.